Tuesday, December 13, 2011

December 12, 13

Continue working on 2.1.7 and 2.1.8...be ready to build trusses on Thursday or Friday.

Friday, December 9, 2011

December 8, 9

Topic: Truss Design
Assignments:
2.1.7 Truss Calculations
2.1.8 Truss Design
Both due after break
Notes:
Document failing points of trusses and calculations in your engineering notebook after testing your trusses. Begin brainstorming for truss design.

December 7

Topic: Truss Design
Assignments:
2.1.7 Truss Calculations
2.1.8 Truss Design
both due after break
Notes:
Continue working on 2.1.7 documenting in your engineering notebook all of your work.

December 5, 6

Topic: Truss Design
Assignments:
2.1.7-Truss Calculations
2.1.8 Truss Design
both due after Christmas break
Notes:
Finish building trusses 1 and 2...each group of 4 needs two truss #1s and two truss #2s
When not activly working on 2.1.8, you should be working on 2.1.7 documenting your work in your engineering notebook.

Friday, December 2, 2011

December 1, 2

Turn in 2.1.6 Step by step truss systems

Begin working on 2.1.8 Truss Design...follow the procedure outlined to make sure you don't skip steps.

In your down time from 2.1.8 (waiting on glue to dry...etc) work on 2.1.7

2.1.8 and 2.1.7 will be due right after christmas break.

Tuesday, November 29, 2011

November 29, 30

Topic: Calculating Truss Systems
Assignments: 2.1.6 due on Thursday/Friday
2.1.7 when done with 2.1.6

Monday, November 28, 2011

November 23, 28

Topic: Calculating Truss Systems
Assignments:
2.1.6 Step by Step Truss System due Tuesday/Wednesday

November 21, 22

Topic: Calculating Truss Systems
Assignments:
2.1.4 Turn In
2.1.5 Turn In
2.1.6 Step by Step Truss System due Tuesday/Wednesday of next week
Notes:
Calculating Truss Forces PPT

Thursday, November 17, 2011

November 17, 18

Topic: Calculating Force Vectors and Moments
Assignments:
2.1.4 Force Vectors due Mon/Tue
2.1.5 Moments due Mon/Tue
2.1.3 Free Body Diagrams...due today
Trig Review...due today

Notes:
Force Vectors PPT
Moments PPT

Tuesday, November 15, 2011

November 15, 16

Topic: Free Body Diagrams and Trigonometry Review
Assignments: 2.1.3 Free Body Diagrams and Trig Review worksheet(odds) due Thursday
Notes: Free Body Diagrams PPT

Monday, November 14, 2011

November 14

Introduction to Structural Member Properties
Groups: None
Assignments
1.3.4 due Wednesday-no class time
2.1.1 Centroids--we will continue working on this for a few class periods as time allows
2.1.2 Beam Deflection-due Wednesday

Notes
Introduction to Structural Member Properties power point
completed 2.1.2 together with the exception of #17 which is homework.

Wednesday, November 9, 2011

November 9

EARLY RELEASE- PARENT TEACHER CONFERENCES

Topic
Structural Member Properties and Beam Deflection

Assignments
1.3.4-due today
2.1.1-due today
2.1.2 Beam Deflection Due Tuesday

Groups: None

Notes: Introduction to Structural Member Properties PPT

November 8

Groups 4, 2, 3: Activity 2.1.1

Groups 1, 5, 6: Activity 2.1.1

Groups 7, 8, 9: Calculations on 1.3.4

Monday, November 7, 2011

November 7

Topic: Centroids
Assignments: 1.3.4 and 2.1.1 are due at the start of class on Wednesday...no class time available on that day for work.
Groups: Same

Friday, November 4, 2011

November 4

Groups 4, 2, 3: Make Up Day...finish calculations, missing assignments, etc

Groups 1, 5, 6: Calculations for 1.3.4 including economics and r-value

Groups: 7, 8, 9: Test insulation

Thursday, November 3, 2011

November 3

Topic: Centroids
Groups: Same
Assignments: Turn in 1.3.4 if not already  done
2.1.1 Centroids due next class

Notes: Centroids PPT

Wednesday, November 2, 2011

November 2

Groups 1, 5, 6: Test Renewable Insulation, start calculations

Groups 4, 2, 3: Finish calculations from your renewable insulation activity

Groups: 7, 8, 9: Finish centroid activity, complete any missing/incomplete assignments.

Tuesday, November 1, 2011

November 1

Topic: Introduction to Statics
1.3.4 Renewable Insulation Calculations
Groups: Same
Assignments: 1.3.4 due end of class
Notes: Introduction to Statics power point presentation

Monday, October 31, 2011

October 31

Groups 4, 2, 3: Test renewable insulation and record in excel spreadsheet
Groups 1, 5, 6: Make up time...finish missing or incomplete assignments
Groups 7, 8, 9: Take notes on statics and centroids. Complete 2.1.1 Centroids due after parent teacher conferences.

Friday, October 28, 2011

October 28

Finish Data collection from 1.3.4
Attend counselor conference
We will do calculations from 1.3.4 on Monday.

Thursday, October 27, 2011

October 27

1.3.4 Renewable Insulation Build Day
1.3.4 due Monday
Groups: Same
Record research, cost estimates, and modifications in engineering notebook.

Wednesday, October 26, 2011

October 26

Renewable Insulation Test
Same
1.3.4 packet is due end of class on Friday.
Notes: Complete Activity 1.3.4 as you gather data.

Tuesday, October 25, 2011

October 25

Topic: Renewable Insulation
Assignment: 1.3.4 Renewable Insulation due Monday 10/31
Groups: New Today
Notes: Record research, cost estimates and design modifications in your engineering notebook.

Monday, October 24, 2011

October 24

Renewable Insulation Build Day
Same Groups as Last Class
Assignment: 1.3.4 Due Wednesday
Notes: Record research notes, design modifications, and cost estimates in your engineering notebooks

Thursday, October 20, 2011

October 20, 21

Topic: Renewable Insulation
Group Members: New Groups Today
Assignment: 1.3.4 Renewable Insulation Design Due Monday
Notes: Record research notes and cost estimates in engineering notebook

Tuesday, October 18, 2011

October 18 , 19

Topic: Thermodynamics
Groups: None
Assignment: 1.3.3 Thermodynamics, due at the end of class.

Notes: Viewed Powerpoint on Thermodynamics and completed 1.3.3 as notes during the presentation,

Friday, October 14, 2011

October 14

Topic: Finish Up Lessson 1.2
Groups: None
Assignments:
1.2.5 due today
1.2 key terms due today
finish up these assignments if necessary
1.2.4
1.2.3
1.2.2
1.2.1
Notes: None

Thursday, October 13, 2011

October 13

Topic: Circuit Calculations
Groups: Same
Assignments:
1.2 Key Terms due Monday
1.2.1 due last class, presentations are today
1.2.2 due last class--if you forgot to turn it in, or didn't put a name on yours, please turn it in today
1.2.3 due today
1.2.4 due at the end of class today
Notes:
Viewed PPT on 1.2.1 Energy Sources
Completed 1.2.4 due at the end of class.

October 12

Topic: Electrical Efficiency
Groups: Same Partners
Assignments:
1.2 Key Terms due today
1.2.1 was due last class
1.2.2 was due last class--if you didn't turn it in already, or forgot to put your name on it, please turn it in today
1.2.3 was due last class
1.2.4 due today
1.2.5 due Thursday
Notes:
Viewed PPT on 1.2.1 Energy Sources
Viewed PPT on Work, Energy and Power and took notes in our engineering notebooks
Completed 1.2.5 Mechanical System Efficiency

Tuesday, October 11, 2011

October 11

Topic: Electricity
Groups: Same Partners
Assignments: 1.2 Key Terms Due 10-13
1.2.1 Energy Sources PPT due Today
1.2.3 Electrical Circuits Simulation due Today
1.2.4 Electrical Circuits Practice Problems due 10-13
Notes: Work day on 1.2.1, 1.2.3, 1.2.4 and make up work.

Thursday, October 6, 2011

October 6, 7

Topic: Black Hills Power Corporation Tour
Groups: None
Assignment: 1.2.2 Energy Distribution due Tuesday
Notes: Toured Black Hills Power and asked questions of a team of engineers lead today by Carly Miller. Answered the questions in the 1.2.2 worksheet.

October 5

Topic: Electrical Circuts
Group: Same partners
Assignments: 1.2.1 Energy Sources power point slides due today
1,2,3 Electrical Circuits Simulation due today
1.2.4 Electrical Circuits Practice problems due Wednesday
Notes: worked on the projects that are currently assigned.

Monday, October 3, 2011

October 3,4

Topic: Introduction to Electricity
Group: Same partners from 1.2.1
Assignments and Due Dates: 1.2 Key Terms (Due October 12, 13)
1.2.1 Due End of Class Today (Presentation will be on October 5, 6)
1.2.3 Electrical Circuits, due End of Class on October 5, 6

Notes: We viewed the Introduction to Electricity Power Point presentation
Finished 1.2.1 if necessary
Began working on 1.2.3 Electrical Circuits Simulation

Thursday, September 29, 2011

September 29, 30

Topic: Energy Sources
Group Members: New Partners (Luck of the draw)
Assignments: 1.1.6 due today!
1.2 Key Terms, extra credit due by the end of 1.2
1.2.1 Energy Sources due Monday/Tuesday.

Notes: Demonstrated our builds from 1.1.6
Viewed brief Power Point presetnation over Energy Sources
Discussed Key Terms
Discussed requirements for 1.2.1 and completed the two power point slides

Self Assessment:

Tuesday, September 27, 2011

September 27, 28

Topic: Energy Sources and Compound Machine Design
Groups: Same
Assignments: 1.1.6 build due at the end of class, documentation due at the start of next class. No more class time to work on this project after today.
Notes: Viewed power point presentation on Energy Sources to begin thinking about the next lesson.

(Power school was down when I went to grade daily grades from last class...will be graded after today.)

Friday, September 23, 2011

September 23, 26

Topic: Compound Machine Design Work Day
Assignment: 1.1.6 due on Septemeber 27/28?
Group Members: Same as 9-21, 22
Notes: Began working right away trying to get as close as possible to being finished with 1.1.6.
Summary:
Self Assessment:

Wednesday, September 21, 2011

September 21, 22

Topic: Compound Machine Design
Group Members: New Partners
Assignments: 1.1.4 due today
     1.1.5 due today
     Start 1.1.6 tenative due date is Sep 27, 28
Notes: Viewed power point presentation on Fischertechnik Mechanisms
Viewed video of compound machine design examples. Click Here for Examples
Discussed Design Requirements and Rubric for the Compound Machine Design project
Began Brainstorming and drawing (These pieces of the project should be your goal for today)

Tuesday, September 20, 2011

September 19, 20

Today in class we...

Turned in Ch1: 73-86
Reviewed ideas about Transformations...if you still need more help on transformations visit this site.
Completed Ch1 87-91 in class to discover rotational, reflection, and transformation symmetry
HOMEWORK: Ch1: 92-96, 100-103 due on 9-21/22

Monday, September 19, 2011

September 19, 20

Topic: Gears, Pulley Drives and Sprockets Continued
Group Members: Same
Assignment: 1.1.2 Simple Machines Practice Problems ALL Due End of CLass
     1.1.3 Gears Due Today
     1.1.4 Pulley Drives and Sprockets due next class, 9-21/22
     1.1.5 Gears, Pulley Drives and Sprockets Practice Problems due next class, 9-21/22

Notes: Work day for the 4 assignments on the table (or any make up work if necessary!)
Self Assesment __/4+___/3+___/3=___/10

Thursday, September 15, 2011

September 15, 16

Topic: Gears, Pulley Drives and Sprockets
Group Members:
Assignments:
**1.1.2 all problems due 9/19 or 20
**1.1.3 Gears due 9/19 or 20
Notes:
Viewed power point presentation on Gears, Pulley Drives and Sprockets. Took notes in our engineering notebook.
Completed Activity 1.1.3 Gears due next class
Finished 1.1.1 if necessary
Received grade print out

REMINDERS:
Robotics Club Meets Thursdays in room 121 at North Campus
Energy Resources Club starts October 5th in room 121 at North Campus
Field Trip Release Forms due back by the field trip on October 6 or 7.

Tuesday, September 13, 2011

September 13, 14

Topic: Simple Machines Investigation

Assignment: 1.1.1 all: DUE end of class
1.1.2 Problems 1-26: DUE next class

Notes:
Today in class we...
Continued working on activity 1.1.1 with the goal of finishing by the end of the period. Teams were encouraged to divide up the parts in order to complete the assignment in the given time.

REMINDERS:
Field Trip on October 6 (5th period) and 7 (1st period)...Bring Back Signed Release Form!
Robotics Club Meets Thursdays after school in Room 121 at North Campus
Energy Resources Club will begin meeting in October...ask Mrs. Cone for information!

Monday, September 12, 2011

September 9, 12

Today in class we...

Continued looking at simple machines, in particular the inclined plane, the wedge and the screw
Continued working on Activity 1.1.1. Should be done with part 1 by the end of the day, when finished with part 1 begin working on part 2.
Continued working on Activity 1.1.2. Problems 1-17 should be finished by Tuesday/Wednesday

ANNOUNCEMENTS
**Field trip to Black Hills Power Plant 5th period on October 6, 1st period on October 7
**Robotics Club meets Thursdays in Room 121 at North Campus from 3:30-5:00
**Energy Resources Club will begin meeting on Wednesdays in October
Ask me about any of these if you have questions or are interested...Thanks!

Wednesday, September 7, 2011

September 7, 8

Today in class we... Completed Activity 1.1.1 in class (due at the end of class today) Discussed Field Trip on October 6, 7...Will remind students as time gets closer. Release forms will be given out on September 12, 13 due back before the trip. Field Trip Details: Black Hills Power Plant 7:45-11:20 (So you will miss either 2nd or 6th period, make sure to get your assignment in advance) Tour the facility, Meet with engineers on location for information and a Q&A session. Homework: Start working on Activity 1.1.2. Should get the first 5-9 problems done if possible.

Friday, September 2, 2011

Simple Machines/ Activity 1.1.1

Today, September 2, 6, in class we... Turned in signed syllabus if not already done...this will become a zero if not turned in by September 9. Finished taking notes on the first three simple machines Were introduced to the fischertechnik parts and were divided up into teams Began working on Activity 1.1.1 Part 1...part one should be finished by the end of class on the 7th/8th.

Thursday, September 1, 2011

Engineering Notebook/Mechanisms

Today (August 31/September 1) in class we...

Turned in: Signed Syllabus
Walked to the Tech Center Room 211
Toured the Tech Center
Set up our Engineering Notebooks
Viewed a power point presentation on Engineering Notebooks
Started viewing a power point presentation on Mechanisms, will finish this presentation on Friday/Monday
Summary and Self Assessment in Engineering Notebooks.

Homework: Read through sample engineering notebook entries and bring questions to class on Friday/Monday.

Monday, August 29, 2011

Welcome to the school year

Welcome! Today is the first day of the 2011-2012 school year.

Today in class we:
Read through the syllabus
Went to the computer lab and investigated careers in engineering
Wrote a summary of our investigation

Wednesday/Thursday: we will tour the tech center and set up our engineering notebooks. See you then.


- Posted using BlogPress from my iPhone

Wednesday, June 1, 2011

May 31

Today in class we...

Completed the final exam. Since we only covered approximately 2/3 of the curriculum, I adjusted the score by 33 points.

Friday, May 27, 2011

May 26

Today in class we...

Reviewed for the final exam. Follow the link in May 20 post to find the practice tests and review powerpoints.

Wednesday, May 25, 2011

May 24

Today in class we...

Turned in the projectile launchers and all related documents

Tested our projectile launchers and competed for longest distance and greatest accuracy

COUNTDOWN
Thursday: Review
Tuesday: Final Exam
Thursday: Make Ups

Friday, May 20, 2011

May 20

Today in class we...

Continued working on Projectile Launcher...due on Tuesday.

Recieved Final Exam Study Guide

Please visit this website for practice tests and review information for each of the topics covered this year.

Wednesday, May 18, 2011

May 18

Today in class we...

continued working on our projectile launchers due on Tuesday

May 16

Today in class we...

Reviewed checkpoints for the ping pong ball launcher project.

Competition will be on Tuesday May 24

Friday, May 13, 2011

May 12

Today in class we...

Discussed due dates to keep our project on time...

Due today: Brainstorming sketches (one from each group member)

Due Monday: Decision Matrix and Final Design Solution sketch or 3-D model

Due Friday: Final Design and Design Modifications Chart

Due Tuesday: The Projectile Launcher and Documentation (Title Page, Table of Contents, Brainstorming Sketches, Decision Matrix, Final Design Drawing, Design Modifications Chart, Reflection, References)

Worked on Decision Matrix and Final Design Drawing due on Monday.

May 10

Today in class we...

Finished our discussion on Projectile motion.

Began brainstorming for the Projectile Launcher project. Each group member is required to bring one sketch of a proposed idea to class on Thursday.

Monday, May 9, 2011

May 6

Today in class we...

Turned in Career demand, salary, and education papers for 20 points extra credit.

Completed 4.1.2 Candy Statistics, due at the end of class.

Began discussion of Projectile Motion and introduced our final design project 4.3.1 Projectile Launcher.

May 4

Today in class we...

Turned in career demand, salary and education papers for 30 points extra credit.

Completed conversations regarding probability and statistics and began working on 4.1.2 Candy Statistics due end of class on Friday.

Monday, May 2, 2011

May 2

Today in class we...

Turned in our extra credit Career Demand, Salary and Education papers for 40 points.

Completed activity 4.1.1 Data Exploration, due at the end of class.

April 28

Today in class we...

Turned in our extra credit Career Demand, Salary, and Education papers.

Finished viewing PowerPoint presentations on Probablity and Statistics.

Began Activity 4.1.1 Data Exploration.

Due end of class on Monday.

Tuesday, April 26, 2011

April 26

Today in class we...

Completed the Unit 4 Key Terms Crossword puzzle

Took notes on the Probability Power Point presentation.

Wednesday, April 20, 2011

April 19

Today in class we...

Set up our machines from 3.1.7

Presented problems and solutions to the class

Turned in the documentation for 3.1.7

Put away fischertechnik parts

April 15

Today in class we...

finished 3.1.7 due on Tuesday

Wednesday, April 13, 2011

3.1.7 Due Tuesday April 19

Click Here for the necessary documentation needed for the project 3.1.7.

April 13

Today in class we... Continued working on 3.1.7. Friday will be our last working day on this assignment. Tuesday will be our day to share our projects and to clean up the fischertechnik parts.

Career Demand, Salary, and Education

Click Here for the Career Demand, Salary, and Education Assignment. This assignment will be due on April 28th.

Tuesday, April 12, 2011

Wednesday, April 6, 2011

April 5

Today in class we...

Finished assigning problems from 3.1.7. See poster in classroom.

Worked on starting 3.1.7. This project is due on April 15th.

Monday, April 4, 2011

April 1

Today in class we...

Turned in 3.1.6

Considered and selected problem to solve for 3.1.7 (see list in classroom for open options)

Began work on 3.1.7

Wednesday, March 30, 2011

March 30

Today in class we... Turned in 3.1.5 Variable Functions Completed 3.1.6 Open and Closed Loop Systems due Friday

Tuesday, March 29, 2011

March 28

Today in class we...

Turned in 3.1.3 and 3.1.4

Completed 3.1.5 variable functions due on Wednesday.

Thursday, March 24, 2011

New Feature: Follow by Email!

If you are interested in having posts from this blog delivered automatically to your email inbox, please enter your email address at right. You might also leave me a comment so that I know you are reading. Thanks!

Tuesday, March 22, 2011

March 22

Today in class we...

Turned in 3.1.1 Inputs and Outputs and 3.1.2 Flowcharting

Completed 3.1.3 Basic Programming, have Mrs. Cone sign off after viewing your program's functionality.

Friday, March 18, 2011

March 18

Today in class we...

Worked on finishing 3.1.1 Inputs and Outputs and 3.1.2 Flowcharts.

These two activities should be done after today. (In other words due Tuesday)

Thursday, March 17, 2011

March 16

Today in class we...

Met in the drafting room due to early release

Viewed Flowchart PowerPoint presentation

Started working on Activity 3.1.2 Flowcharts

Friday will be a day to finish 3.1.1 and 3.1.2 and they will both be due on Tuesday.

Monday, March 14, 2011

March 14

Today in class...

Get a laptop, Robo Interface, power cord, and USB cable

Go to the PLTW Class drive on the computer, POE folder, ROBOPRO folder

Open ROBOPRO Windows 7 document

Hold control and click on the link to open the installer

Install ROBOPRO

Connect Interface to laptop

Open ROBOpro software...follow instructions on the test interface page.

Complete activity 3.1.1

If you finish, you may start working on 3.1.2

Friday, March 11, 2011

March 10

Today in class we...

Worked on finishing our Bridge Design Projects they were due at the end of class

Worked on Career Demand, Salary and Education paper. This is due on April 11.

Tuesday, March 8, 2011

March 8

Today in class we...

Assigned Career Demand, Salary and Education Research Project. This project is due on April 11th.

Discussed Key Terms relating to Machine Control Systems. Assigned Key Terms Crossword Extra Credit Assignment due on March 10th.

Disassembled and put away the fishertechnik parts from the previous activity.

Assembled the fishertechnik parts required for activity 3.1.1 and learned how to test connectivity. Add reference sheet regarding testing connectivity to Engineering Notebooks.

Worked on completing the two projects that are currently in progress...
1) Activity 2.4.1 Bridge Design due Thursday March 10
2) Career Demand, Salary, and Education paper due April 11

Engineering Notebook Summary:

What career are you planning on researching for the CDSE paper?
What steps do you need to finish for the Bridge Design Documentation?

Friday, March 4, 2011

2.4.1 Bridge Design Work Day 2

Today, March 4, in class we...

finished working on our bridge design project including all of the documentation for the project

the final project is due on Thursday March 10

today is the final day to work on this project in class

2.4.1 Bridge Design Work Day

Today, March 2, in class we...

had a substitute teacher

worked on completing our bridge design project

the due date for this project has been extended to Thursday March 10 due to the missed class period on Monday

Fractals

Today, February 28, in class we...

had a substitute teacher

watched a movie on fractals

Thursday, February 24, 2011

2.4.1 Bridge Design

Today, February 24, in class we...

Reviewed requirements for the bridge design project. Decided on a final due date of March 8th.

Worked on bridge designs.

2.4.1 Bridge Design Continued

Today, February 24th, in class we...

Continued working on the bridge design contest. Remember to be documenting your progress and how your design changes over time.

Eagle Butte Field Trip

Today, February 22nd, in class we...

Toured the Tech Center and Eagle Butte Coal Mine.

2.4.1 Bridge Design

Today, February 17, in class we...

Reviewed the requirements for project 2.4.1 and discussed the design process. If you have questions about what is required, please see Mrs. Cone.

Worked on designing the most efficient bridge using the West Point Bridge Design software.

REMINDER: FIELD TRIP ON TUESDAY. Bring your release forms.

Tuesday, February 15, 2011

2.4.1 Introduction to West Point Bridge Designer

Today, February 15, in class we...

Discussed field trip to Eagle Butte Mine on Tuesday Feb 22nd...parent release forms need to be returned by Tuesday.

Installed West Point Bridge Designer on laptops and explored the software using steps 1-20 in the 2.4.1 packet.

Exploration and data from steps 1-20 due at the end of class.

Friday, February 11, 2011

2.2.2 Manufacturing Process

Today, February 11th, in class we...

Discussed how to find the area, volume and mass of our component in Inventor: Right Click on the name of the part in the part organizing window on the left hand side of the screen. Go to iProperties, click on the Physical tab, select your best guess for the material your component is made from, and it will calculate the mass, area and volume. Record as part of 2.2.1.

Discussed activity 2.2.2: Research how your component is manufactored. Create an illustration depicting this process from start to finish in your engineering notebook. Make sure you site your sources.

2.2.1 and 2.2.2 are due on Tuesday.

2.2.1 Part 2

Today, February 9th, in class we...

Completed part 2 of activity 2.2.1 using AutoDesk Inventor. The modeling is due on Friday...

We had trouble finding where to calculate the area, volume, and mass of the component...I will research and provide an answer on Friday...

2.2.1 Part 1 Step 9

Today, February 7th, in class we...

Completed step 9 of the product analysis activity 2.2.1 due by Wednesday

Thursday, February 3, 2011

2.2.1 Part 1 Steps 3-8

Today in class we...

Completed steps 3-8 of activity 2.2.1 Product Analysis due on Monday

Wednesday, February 2, 2011

2.2.1 Introduction to Materials

Today in class we...

Turned in write up for 2.1.8.

Completed 2.2 Crossword Puzzle for extra credit.

Viewed powerpoint presentation for "Introduction to Materials"

Completed Steps 1 and 2 of Part 1 of 2.2.1 due on Tuesday (UPDATE: DUE THURSDAY DUE TO "SNOW" DAY)

Thursday, January 27, 2011

2.1.8 Test

Today in class we...

Tested our trusses. Congratulations to Erin, James, Dalton, and Kaeleigh for building the most efficient trusses.

Completed the reflection for 2.1.8 in our engineering notebooks (Due at the start of class on Friday)

Wednesday, January 26, 2011

2.1.8 Build Day 2

Today in class we...

Continued building our trusses.

Your trusses need to be ready to test on Wednesday. Come prepared to test trusses and summarize your learning and complete your calculations. Final write up for the truss design project is due on Friday.

Friday, January 21, 2011

2.1.8 Build Day 1

Today in class we...

Started building the trusses for 2.1.8. We will continue building on Monday and the truss needs to be completed at the start of class on Wednesday.

Wednesday, January 19, 2011

2.1.8 Design

Today in class we...

Discussed Engineering Notebooks for 2nd semester

Introduced MDSolids for completing truss calculations

Worked on our design for 2.1.8, design is due at the start of class on Thursday.

Completed first Engineering Notebook Entry

Wednesday, January 12, 2011

Final Exam

Today in class we...

Completed 2.1.7 Truss Calculations due Friday

Completed Final Exam due Friday

Monday, January 10, 2011

Truss Construction Field Trip

Today in class we...

Met with Mr. Pridgeon at North Campus in the Construction Shop to discuss truss construction and design

Assigned Semester Take Home Final Exam due on Friday

Semester Countdown:

Wednesday: Work on 2.1.7 and Final Exam

Friday: 2.1.7 and Final Exam Due Today...work on 2.1.8 design

Activity 2.1.8 Testing

Today in class we...

Tested the first two trusses from 2.1.8. A couple of groups did not get to test...they will have time next week to break their trusses.

Continued work on 2.1.7...due on Friday January 14

Discussed meeting at north campus construction shop on Monday to visit with Mr. Pridgeon about truss design and construction in order to prepare for designing the final truss for 2.1.8.

Semester Countdown:

Monday: Meet with Mr. Pridgeon at North Campus. Assign Take Home final

Wednesday: Work on 2.1.7 and Take Home Final

Friday: work on 2.1.7 and Take Home Final...start designing 2.1.8 truss

Tuesday, January 4, 2011

2.1.8 Truss Design

Today in class we...

Discussed the completion of activity 2.1.7. This assignment is to be worked on during down time while building the trusses for 2.1.8. 2.1.7 is due on Wednesday 1/12.

Started 2.1.8 by building the two trusses provided. Use tagboard for the gussets. The two trusses should be built by the end of class today so that they can dry for testing on Thursday.